Tuesday, January 14, 2014

The "House of Health" will be ready by summer - Journal of Reggio

Montecchio: the new facility will host all of the health services in the district also continuing work on the construction of the new wing of the hospital

MONTECCHIO. Continue promptly its work for the construction of the new wing of the hospital, “Franchini” and the great structure that will host the so-called “House of Health”, which is the building that will host the new headquarters of the District Centre of Prevention and Community Medicine, which according to forecasts, could be completed by the summer.

In recent days, the mayor Paul Hills has carried out an inspection on construction of the “Franchini” and the House of Health, accompanied by the heads of companies executing to check the progress of the work.

new spaces Hospital jobs are at an advanced stage: by March, in fact, will be completed the first and second floor of the new wing, which will be placed respectively departments of obstetrics-gynecology and long-term care .

Into April, will also be moved temporarily to the ground floor of the new wing also the ER.

Following the current building will be completely renovated emergency department and the service will return to his home completely rebuilt before the summer of 2015.

At that point, the ground floor of the new wing of the hospital montecchiese assume its functionality ultimately dedicated to the clinics.

the construction of the imposing structure of the House of Health, which once completed will house all social and health services now scattered throughout the territory, is proceeding at full speed. The work, in fact, had been broken off in the second half of 2012 due to the difficulties of Orion, which was taken over by the contract the company Siteco.

January 14, 2014